Mbarara politicians, technocrats clash over Shs 1.2bln returned to treasury
MBARARA, November 27, 2026 — Mbarara City’s political leaders have clashed with senior technical officials over the return of Shs 1.2 billion earmarked for upgrading Major Victor Bwana and Makhan Singh road links to the government’s Consolidated Fund, a development that has stalled the project and exposed the city council to a potential lawsuit.
The funds were part of a Shs 1.99 billion allocation that also catered for contract variations and retention payments for Buremba road.
The controversy emerged during a heated council meeting in which Mbarara City Mayor Robert Mugabe Kakyebezi accused Chief Finance Officer [CFO] David Mbarekye and the town clerk’s office of negligence, saying their failure to confirm the project commitments with the Bank of Uganda resulted in the money being returned to the treasury at the end of the financial year.
The development has forced the contractor, Jagens and Technical Services, to abandon the site over delayed payments and issue a notice of intention to sue the city council for interest, damages and legal costs.
The 0.16-kilometre road project was initially scheduled to take three months. However, despite an extension of the contract period to November 30, 2026, the works remain stalled.
“Major Victor Bwana and Makhan Singh links, which the contractor Jagens and Technical Services started working on, stalled because of the negligence of staff that led to the money returning to the Consolidated Fund,” Kakyebezi told councillors.
He said the money had been held at the Bank of Uganda under letters of credit, but the CFO failed to confirm whether it had been committed to the specific project.
Kakyebezi said the contractor had since issued a notice of intention to sue the city for interest and damages, in addition to Shs 10 million in legal fees.
He also raised concerns about the unfinished road, saying runoff water was damaging neighbouring properties belonging to residents, including Evaristo Kategaya and Kacuma.
Council demands answers over stalled project
Deputy City Town Clerk Simon Ejau declined to provide a definite explanation on when the money would be reallocated to the project, referring councillors to the finance department.
“The CFO is around; let him answer, as he is in a better position to explain,” Ejau said.
He confirmed that legal action against the city was looming, adding that he had signed a letter of intention to sue.
“As far as the details of the contract period extension go, I do not have full clarity,” he said.
City Speaker Bonny Tashobya Karutsya criticised the lack of clear communication among city officials, demanding clarification on the extended contract period and the future of the road project.
“The contract was extended, so people want to know up to when. That is what members of the council want clarity on,” Tashobya said.
“We do not want administrative camouflage; we want to know whether we are having our road links opened or whether we are losing the money.”
Kakyebezi further disclosed that his executive had petitioned the Inspectorate of Government (IGG) and the Regional Criminal Investigations Department [CID] to investigate the city’s financial operations.
He cited other delayed payments, including funds meant for workers involved in the measles-rubella vaccination campaign and statutory remittances to city divisions.
“We went to the IGG and petitioned, and we also opened a case with the Regional CID to investigate why payments are being delayed and why divisions are lamenting,” he said.
The mayor warned that continued administrative wrangles could undermine service delivery and expose political leaders to public criticism over failures that he attributed to technical officers.
He also expressed concern over the city’s revenue performance, revealing that Mbarara had collected only Shs 2.26bln out of its Shs 11.31bln local revenue target for the 2026/27 financial year between July and October.
“We cannot allow internal infighting and unfacilitated revenue teams to reverse the growth this city has achieved,” he said.
In response, Mbarekye attributed the return of the funds to a procedural error in their classification under letters of credit, saying technical guidance was required before the money could be committed.
“The money will be re-voted back; it was placed under a letter of credit error, and technical guidance was needed before committing it there,” he said.
RCC calls for dialogue
Mbarara City Resident City Commissioner Catherine Helen Kamwine urged the political leadership and technical staff to resolve their differences through dialogue rather than public confrontations.
Her appeal comes amid growing tensions between the two sides, which have been compounded by recent anti-corruption interdictions involving senior city officials.
Kamwine commended the city council for its infrastructure and service delivery achievements despite the challenges, urging leaders to prioritise development.
“I want to thank Mbarara City Council for the work well done despite the challenges we have gone through, because at least we have tangible projects and services to present to the community,” she said.
“I beg that we handle our internal challenges through dialogue before escalating them. We cannot achieve development when we have infighting, because infighting fights development. Let us sit down, reconcile and put all our energies into serving the people.”
Meanwhile, Tashobya urged the city council to prioritise the acquisition of a municipal fire engine to strengthen emergency response and protect businesses and property.
He said recent fire outbreaks, particularly at timber yards, had exposed the city’s inadequate firefighting capacity, with property often destroyed before police fire tenders arrived.
The Speaker noted that the city had already acquired equipment, including a bulldozer, grader, water bowser and revenue enforcement vehicle, and argued that a fire engine should be among its next priorities.
“We need to buy a fire truck to put out fires in Mbarara City. We have bought a bulldozer, a grader, a water bowser and a revenue enforcement vehicle, but we also need to consider people’s lives and businesses,” he said.
He added that protecting businesses was important because they contributed to the city’s revenue through taxes.
“Recently, fire broke out at the timber dealers’ premises, and by the time the police fire truck arrived, everything had turned to ashes. I request members and the executive to prioritise this because fire is also a form of insecurity,” Tashobya said.
https://thecooperator.news/mbarara-city-recognised-for-outstanding-local-revenue-growth/
Buy your copy of theCooperator magazine from one of our countrywide vending points or an e-copy on emag.thecooperator.news