Kotido’s ghost dams: Billions committed, communities still waiting for water

KOTIDO, November 25, 2026 – For years, communities in Kotido district have looked to government investments in dams to ease water shortages, support livestock production and improve livelihoods. However, the condition of two major dam projects during a government monitoring visit on November 18, 2026, has raised fresh questions about the implementation of the projects and the billions of shillings reportedly committed to them.

At Sinat and Kawayongor, the monitoring team found no visible construction activity. There were no workers or machinery at the sites during the inspection, and the expected water infrastructure was not visibly in place.

The findings prompted a strong reaction from the Minister of State for Economic Monitoring in the Office of the President, Hon. Santa Sandra Alum-Ogwang, who expressed disappointment at what she had witnessed.

“What I have witnessed here is so saddening,” the minister said, questioning how a place expected to be a dam could look like a road or runway.

During the monitoring exercise, the two projects were reported to be valued at approximately Shs 19.2 billion for Sinat Dam and Shs 6.9bln for Kawayongor Dam, bringing their combined reported value to about Shs 26.1bln.

The minister blamed the Ministries of Agriculture and Water for failing to ensure that the projects delivered their intended benefits, saying government investments were not translating into tangible results for the people of Karamoja.

She said she would brief President Yoweri Museveni on the findings and that action would be taken where implementation had fallen short.

However, the condition of the sites raises questions beyond the minister’s inspection: How much public money has been spent on the projects, what work has actually been completed, and why are communities still waiting for the water infrastructure they were promised?

Sinat Dam: A history of delays

Concerns surrounding Sinat Dam are not new. Government records show that the project was already behind schedule in 2022, raising questions about why it remained incomplete years later.

The Auditor General’s report on the Ministry of Agriculture for the financial year ended June 2022 recorded that construction of Sinat Valley Dam started on January 4, 2022, under a one-year implementation period.

By October 2022, the project was behind schedule, with physical progress estimated at 40 per cent despite only two months remaining before its planned completion.

The audit report listed Shs 2.259bln as expenditure against the project and attributed the delays to insecurity in the region, which had affected the commencement of planned works.

The report established that the project was behind schedule at the time of the audit. However, it did not establish the total amount eventually paid to the contractor or the project’s final financial position.

The project also featured in a parliamentary discussion in October 2026. On October 21, Agriculture Minister Frank Tumwebaze presented a statement on the performance of his ministry, listing Sinat and Longomorit among dams in Karamoja and Teso that he said were either under construction or nearing completion.

He invited legislators to visit the sites independently and establish their status.

Less than a month later, however, the November 18 inspection found no visible construction activity at Sinat. Although this observation does not establish what work may have been undertaken before the visit, it raises questions about the project’s actual implementation status at the time the minister reported to Parliament.

What work had been completed? What remained outstanding? And why was there no visible activity during the subsequent inspection?

In March 2025, Sinat Dam was valued at approximately Shs 19bln and was still under construction. Once completed, the dam was expected to have a capacity of three billion litres of water.

The planned Sinat Dam is a two-kilometre project in Maaru Subcounty, with a reported cost of Shs 25bln and a targeted completion date of December 2022.

The Ministry of Agriculture and the contractor need to explain the project’s history, account for the work completed and provide a credible timeline for bringing the dam into operation.

Communities continue to struggle for water

For Kotido’s pastoralist communities, the delays are more than a construction dispute. They affect access to water for livestock, household consumption and agricultural production.

District LCV Chairperson Lotee Paul Komol told the monitoring team that communities continued to struggle to access water, with local leaders sometimes having to seek assistance from neighbouring areas.

He said completing the dams would ease pressure on pastoralists, support irrigation and improve agricultural production.

Komol urged the Ministry of Agriculture to return to the project sites and complete the works. He also raised concerns about other water facilities, including Kailong and Longor dams, which he said had failed to deliver the expected results despite reported government interventions.

He further told the team that only three of the district’s 45 valley tanks were functional, a claim that requires technical verification by the relevant district and water authorities.

Resident District Commissioner Charles Ichogor said the relative peace in the region should now allow government and local leaders to concentrate on development, particularly water infrastructure.

He argued that water shortages were worsening the effects of drought, damaging crops and forcing communities to seek water outside the district.

For a district whose economy depends heavily on livestock and agriculture, unreliable water infrastructure affects livestock survival, crop production, household incomes and farmers’ ability to withstand prolonged dry spells.

The minister acknowledged that recurrent drought, unreliable water supplies, limited market access and poor road infrastructure remained major challenges affecting development in Karamoja.

Kacheri health project raises further concerns

The monitoring exercise also exposed concerns about delayed public infrastructure in the health sector.

During the meeting, Kotido leaders raised questions about the construction of Kacheri Health Centre IV, an upgrade of the existing Health Centre III.

The project was included in the Ministry of Health’s Karamoja Infrastructure Development Project Phase II and handed over to Mangron Investment Limited.

In January 2025, Uganda Radio Network reported that the wider project package was valued at Shs 4.28bln and included the Kacheri facility, improvements at Lokitelaebu Health Centre III and the construction of district health department offices.

The planned upgrade at Kacheri included a theatre, maternity ward, outpatient department and a four-stance pit latrine. The wider package was expected to take 18 months to complete.

During the November monitoring exercise, the facility remained incomplete. The inspection raised concerns about outstanding works, including the installation of window frames, electrical wiring and plastering.

Komol questioned the delay, noting that the Chief Administrative Officer had reportedly indicated that internal plastering had been undertaken. He also raised concerns about funding releases from the Ministry of Health.

The delay is significant because residents of Kacheri, Maaru, Kapeeta and neighbouring communities are expected to benefit from improved access to health services, including maternity and surgical care.

Emyooga SACCOs struggle with loan recovery

Beyond infrastructure, the monitoring team examined the performance of government-backed enterprise and livelihood programmes, including Emyooga and the Parish Development Model [PDM].

The experience of Jie County Local Leaders SACCO illustrated some of the difficulties facing community-based financing initiatives.

Natuk Faith, a representative of the SACCO, told the team that the group had 189 members organised into 15 associations, of which 13 were active.

The SACCO received Shs 20mln in December 2019, but operations only began in July 2021.

The representative attributed repayment difficulties to the effects of COVID-19, insecurity, hunger and livestock raids, which affected members’ ability to repay loans and made it difficult for the SACCO to monitor borrowers.

The group said loan recovery efforts resumed in 2024 following guidance from the Resident District Commissioner.

The representative reported that some associations had made progress in repaying the funds, although recovery remained uneven.

Rikitae Association was reported to have achieved full recovery, while Napupum was also mentioned among the associations that had returned funds. Other associations were still expected to repay their outstanding loans.

The representative acknowledged that lending to individuals had created challenges and suggested exploring alternative ways of growing the SACCO’s resources, including participation in cattle trading.

The minister questioned the SACCO’s recovery arrangements and encouraged beneficiaries to fulfil their repayment obligations.

The experience illustrates how economic shocks affecting members can undermine the sustainability of community institutions established to support them. Loan recovery, effective monitoring, member accountability and borrowers’ ability to withstand economic shocks remain critical to the survival of such SACCOs.

A different experience from Karachuna SACCO

Not all the SACCO experiences presented to the monitoring team were negative.

A representative of the Karachuna SACCO, associated with the Tigogong Ekisil group, told the team that the group had received Shs 4 million and had started building its operations around teamwork, joint business activities and shared knowledge of livestock trading.

The representative said members had established business links in Moroto and Kenya, enabling them to access wider markets.

The group had also formed a recovery committee involving members from different divisions to follow up on savings and loan repayments.

According to the representative, rather than using force, the committee contacts members and follows up with them on their designated saving days.

The minister welcomed the group’s progress and discussed the need to recognise and support well-performing groups. An additional Shs 50mln and a motorcycle were mentioned during the discussions, although the status and approval of the proposed support require confirmation.

The group’s experience offers a useful lesson for community financing programmes: strong internal organisation, market connections and consistent follow-up can contribute to better financial discipline.

However, the wider question remains whether such practices can be strengthened across other SACCOs facing repayment difficulties.

Climate-smart agriculture and the cost-sharing challenge

The monitoring discussions also exposed concerns about the accessibility of climate-smart agricultural interventions.

RDC Ichogor told the team that Kotido had registered 453 farmers for a climate-smart agriculture programme, but only six were expected to benefit because participating farmers were required to contribute 20 per cent of the cost.

He appealed for special consideration for farmers in Kotido, arguing that the contribution requirement could limit access for communities already affected by drought and crop failure.

The claim raises questions about whether cost-sharing arrangements are appropriate for vulnerable farmers in a region where recurrent drought continues to undermine agricultural production.

The district needs to establish the exact number of registered and eligible farmers, the required contribution and whether alternative arrangements are available for those unable to raise the money.

Komol also told the monitoring team that many beneficiaries who invested their Parish Development Model funds in agriculture had suffered losses following poor weather conditions.

Some had reportedly invested in livestock, while others experienced crop failure and struggled to recover their investments.

The concerns point to the need to assess whether livelihood programmes are sufficiently adapted to the climatic and economic realities of pastoral and agro-pastoral communities.

Roads, staffing and wider development concerns

Beyond the dams, health facility and enterprise programmes, district leaders raised concerns about road infrastructure, staffing and land use.

Komol said Kotido needed reliable water infrastructure to support production and livestock, while also highlighting the need for improved roads to connect communities and facilitate economic activity.

Kotido Municipal Mayor Irar Peter Abraham described the Moroto-Kotido road as strategically important for economic and social development, including access to Kidepo Valley National Park.

He also raised concerns about the lack of road equipment for Kotido Municipality, saying the municipality had to rely on contractors for much of its road maintenance.

The district chairperson further reported shortages of specialist health personnel and agricultural extension workers, saying the district had a shortfall of 27 extension workers. The staffing figures require confirmation from the relevant district departments.

These concerns are significant because infrastructure investments require functioning institutions and adequate staffing to translate public spending into services and economic opportunities.

Minister promises action

Alum-Ogwang said the purpose of the monitoring exercise was to establish whether government programmes were being implemented as planned, whether facilities were complete and functional, and why some interventions were failing to produce the expected results.

The exercise formed part of a 12-day monitoring programme announced by the Office of the President, covering all nine districts in Karamoja from November 16 to 27, 2026.

The programme was intended to assess infrastructure and wealth-creation interventions, including dams, roads, valley tanks, boreholes, irrigation facilities, PDM and Emyooga.

The minister urged beneficiaries to speak freely about their experiences with government programmes, including PDM, Emyooga and the Karachuna initiative.

She also called on local leaders and district officials to ensure that public resources were protected and that civil servants responsible for implementation were held accountable.

She warned against attempts to frustrate efforts to deal with people found culpable in the management of public resources.

The monitoring exercise has placed responsibility on both central government ministries and local authorities to explain the gaps between planned investments and the services communities are receiving.

For residents of Kotido, the real test will not be the number of monitoring visits conducted or the promises made during meetings. It will be whether the dams are completed, health facilities become functional, roads improve and livelihood programmes deliver lasting economic benefits.

Until then, the sites at Sinat and Kawayongor remain a stark reminder of the gap between government investment commitments and the services communities desperately need.

https://thecooperator.news/kotido-pushes-farmer-led-irrigation-to-boost-food-security/

Buy your copy of thecooperator magazine from one of our country-wide vending points or an e-copy on emag.thecooperator.news

Related Articles

Back to top button